Late Add, On Schedule

Development Story / Production

Late Add, On Schedule.

How we added 300 units after production started — while keeping the original delivery date.

Lightweight WovenProduction Stage+300 Units

Challenge

Additional units after production had already started.

A contemporary womenswear brand added units in two rounds after production was already in progress. We needed to confirm whether the additional volume could be absorbed without affecting the delivery date.

+200

Units

['First addition']

+100

Units

['Second addition']

What We Reviewed

A practical assessment before we made a decision.

We reviewed the key factors to understand whether the additional units could be absorbed without affecting the delivery date.

  • Production Capacity
  • Material Availability
  • Current Schedule
  • Delivery Impact

What We Did

We integrated both additions into the existing production plan.

Instead of restarting production later, we adjusted the line plan, reserved capacity and integrated the additional units in sequence.

Original Production
+200 Units Integrated
+100 Units Integrated
Original ETA Maintained

The Result

+300

Units Added

Original ETA

Maintained

0

Production Restarts

What Made It Work

  • Available material
  • Flexible capacity
  • Early decision

Project Evidence

Documented from the project files.

Material in Production

Material in Production

Same fabric lot, continuous supply.

Production Adjustment

Production Adjustment

Integrated additional units on the same line.

Final Production

Final Production

All units delivered on schedule.